Generated by TaskJuggler 3.8.4 — the source is a text file, the output is static HTML. There is no server, no login, no click-to-edit.
# dependencies are declarative: the scheduler decides dates project rack "Inference rack — phase 1" 2026-10-26 +30d { timezone "Europe/Berlin" task power "Power & electrical" { task audit "Site power audit" { effort 3d } task breaker "240 V breaker" { effort 5d; depends !audit } task rack "Rack, PDU" { effort 2d; depends !breaker } } task bringup "Node bring-up" { task soak "GPU burn-in" { effort 4d depends !power.rack, !network.fw } } task sell "Sell capacity" { task listing "Marketplace listing" { effort 3d depends !bringup.bench, !paper.contract } } }
| id | task | start | end | effort | critical | depends |
|---|---|---|---|---|---|---|
| A · Power & electrical | ||||||
| A1 | Site power audit + load calc | 26 Oct | 28 Oct | 3 d | yes | — |
| A2 | 240 V breaker + circuit run | 30 Oct | 3 Nov | 5 d | yes | A1 |
| A3 | Rack, PDU + cable management | 5 Nov | 6 Nov | 2 d | yes | A2 |
| B · Network | ||||||
| B1 | Order fibre uplink (business) | 27 Oct | 28 Oct | 2 d | no | — |
| B2 | Firewall rules + VLAN split | 31 Oct | 1 Nov | 2 d | no | B1 |
| C · Cooling & room | ||||||
| C1 | Cooling design (airflow, dB) | 28 Oct | 31 Oct | 4 d | no | — |
| C2 | Ducting + intake install | 5 Nov | 7 Nov | 3 d | no | C1, A2 |
| D · Paperwork | ||||||
| D1 | Insurance rider + LLC docs | 26 Oct | 1 Nov | 7 d | no | — |
| D2 | Provider contract review | 4 Nov | 6 Nov | 3 d | no | D1 |
| E · Node bring-up | ||||||
| E1 | GPU node burn-in (3× 24 h soak) | 8 Nov | 11 Nov | 4 d | yes | A3, B2 |
| E2 | Benchmarks + listing photos | 13 Nov | 14 Nov | 2 d | yes | E1 |
| F · Sell capacity | ||||||
| F1 | Marketplace listing application | 16 Nov | 18 Nov | 3 d | yes | E2, D2 |
| F2 | First paid workload live | 20 Nov | 23 Nov | 4 d | yes | F1 |
| October 2026 | November 2026 | |||||||||||||||||||||||||||||
| 26 | 27 | 28 | 29 | 30 | 31 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | |
| A · Power & electrical | ||||||||||||||||||||||||||||||
| A1Site power audit + load calc critical | ||||||||||||||||||||||||||||||
| A2240 V breaker + circuit run critical | ||||||||||||||||||||||||||||||
| A3Rack, PDU + cable management critical | ||||||||||||||||||||||||||||||
| B · Network | ||||||||||||||||||||||||||||||
| B1Order fibre uplink (business) | ||||||||||||||||||||||||||||||
| B2Firewall rules + VLAN split | ||||||||||||||||||||||||||||||
| C · Cooling & room | ||||||||||||||||||||||||||||||
| C1Cooling design (airflow, dB) | ||||||||||||||||||||||||||||||
| C2Ducting + intake install | ||||||||||||||||||||||||||||||
| D · Paperwork | ||||||||||||||||||||||||||||||
| D1Insurance rider + LLC docs | ||||||||||||||||||||||||||||||
| D2Provider contract review | ||||||||||||||||||||||||||||||
| E · Node bring-up | ||||||||||||||||||||||||||||||
| E1GPU node burn-in (3× 24 h soak) critical | ||||||||||||||||||||||||||||||
| E2Benchmarks + listing photos critical | ||||||||||||||||||||||||||||||
| F · Sell capacity | ||||||||||||||||||||||||||||||
| F1Marketplace listing application critical | ||||||||||||||||||||||||||||||
| F2First paid workload live critical | ||||||||||||||||||||||||||||||
Stylised concept built from the project's public documentation and screenshots — not a pixel copy of the product, and not connected to any data.